24) The reporting frequency, report recipients, and content required during project execution is laid out by:
A) The organizational breakdown structure.
B) Scope reporting.
C) The information system architecture.
D) A need-to-know basis.
ANS
B) Scope reporting
- what type of information
- who receives it
- when and how the information is disseminated