Consider the following project Activity’s Name Immediate predecessor Time to complete the job A 3 B 2 C B 4 D C 3 E A, C 1 F D, E 1 1. Draw a network diagram representing this project. 2. Identify the critical path. 3. What is the minimum time needed to complete this project