Tally Company uses job costing. The job cost record for Job A61 on March 1 showed a balance of $5,200. The job was completed on March 16. During March materials requisitions for this job were $2,300. Labor time records for this job in March were $4,000. Manufacturing overhead is allocated based on direct labor cost. The rate is 90% of direct labor cost. How much is the total cost of Job A61?

Respuesta :

Answer:

Total cost= $15,100

Explanation:

Giving the following information:

The job cost record for Job A61 on March 1 showed a balance of $5,200.

Job A61:

March:

Direct materials= $2,300.

Direct Labor= $4,000.

Manufacturing overhead is allocated based on direct labor cost. The rate is 90% of direct labor cost.

MOH= 4000*0.9= $3,600

Total cost= 5,200 + 2,300 + 4,000 + 3,600= $15,100