Answer:
[tex]T_b=4.667\ hr/batch[/tex]
The number of hours required to complete the batch are 4.667 hr
Step-by-step explanation:
Time for each cycle=[tex]T_c[/tex]= Part handling time + Operation time
Time for each cycle=[tex]T_c[/tex]=0.50+1.67
Time for each cycle=[tex]T_c[/tex]=2.17 min
Since Scrap Rate is 5 %=0.05:
Starting quantity of batch is:
[tex]Q_o=\frac{100}{1-0.05}[/tex]
[tex]Q_o=105.26\ Parts[/tex]
[tex]Q_o[/tex]≅106 Parts
Batch Time can be calculated as:
[tex]T_b=T_c[/tex]*(Starting batch quantity)+Setup Time
[tex]T_b=2.17*106+50\\T_b=280.02\ min/batch\\ T_b=4.667\ hr/batch[/tex]
The number of hours required to complete the batch are 4.667 hr