YOPSTAR449 YOPSTAR449 15-04-2020 Business contestada The project team toiled long into the night to develop consequence of failure scores and probability of failure scores as indicated below. What is the overall risk factor for the project? A) Less than or equal to 0.7 B) Greater than 0.7 but less than or equal to 0.8 C) Greater than 0.8 but less than or equal to 0.9 D) Greater than 0.9 Maturity 0.7 Cost 0.4 Complexity 0.6 Schedule 0.6 Dependency 0.8 Reliability 0.8 Performance 0.9